What thirty years in the UK taught us about working in the heat

We spent three decades decorating in the UK, where the enemy is damp and the working window is set by how long a coat takes to dry in a cold room.
Dubai inverts that. Here the substrate can be well above the manufacturer's stated maximum surface temperature by mid-morning, and a coat applied to a hot wall skins on the surface before the body of the film has flowed out. You get a finish that looks acceptable on the day and fails within a year.
So the sequence changed. Exterior elevations are worked against the sun rather than with the clock, starting on the shaded face and following the shadow round. Interior work in unconditioned new-builds happens with the cooling running, which sometimes means paying for a temporary chiller and building it into the quote rather than pretending the problem does not exist.
What did not change is the preparation. A properly filled, sanded and sealed wall behaves the same in forty degrees as it does in eight.